Step#0 : Preparatory work

  1. please find the data and power connection drawings.
  2. please notice our cabinet need be install in a fixed order which shows in pic
  3. Each cabinet have a label on the cabinet`s  HUB, like pic B.

Step#1 Attaching unit Cabinet

  • Check each vertical / horizontal structure with gradient and make sure all structures are straight and at a same level
  • Put 2 cabinets on the middle and tight them together with side locks then tighten them on the structure with the brackets,

Step#2 Installing the cabinet

  • From the middle spread to outside to finish the bottom row, see below
  • Follow above to finish install from bottom to up

Let's move to Cabling

Cabling